Question: Loans are evaluated in a process with two resources. The first resource has a capacity of 2.4 loans per hour. The capacity of the second

Loans are evaluated in a process with two
Loans are evaluated in a process with two resources. The first resource has a capacity of 2.4 loans per hour. The capacity of the second resource is 4.4 loans per hour. The first resource has 1 worker and the second resource has 8 workers. One additional worker is hired who is as productive as the current workers. Instruction: Round your answer to three decimal places. What is the new capacity of this process? loans per hour