Question: LS: MULT 20 LT: 1 Period 1 2 3 4 5 Gross Requirements 66 64 80 68 89 Scheduled Receipts 40 Projected on Hand 30
| LS: MULT 20 | LT: 1 | Period | 1 | 2 | 3 | 4 | 5 |
| Gross Requirements | 66 | 64 | 80 | 68 | 89 | ||
| Scheduled Receipts | 40 | ||||||
| Projected on Hand | 30 | ||||||
| Net requirements | |||||||
| Planned Order Receipts | |||||||
| Planned Order Releases |
In the above MRP matrix, what is the projected on-hand in period 4?