Lucy is in charge of planning and coordinating a project. Following is the activity information for this project.
Time (weeks)
Activity
Preceded By
Optimistic
Most Likely
Pessimistic
Lucy is in charge of planning and coordinating a project. Following is the activity information for this project.
Time (weeks) | ||||
Activity | Preceded By | Optimistic | Most Likely | Pessimistic |
A | -- | 2 | 2 | 4 |
B | A | 8 | 12 | 16 |
C | A | 4 | 8 | 12 |
D | B,C | 2 | 4 | 6 |
E | B | 4 | 6 | 8 |
F | A | 2 | 4 | 6 |
G | D | 2 | 4 | 6 |
H | G | 2 | 4 | 6 |
I | E,F,H | 2 | 2 | 2 |
Requested:
(a) Construct a precedence diagram.
(b) Identify the Critical Path(s) and the expected completion time.
(c) What is the probability that the training program can be completed in 26 weeks?