Question: . M 4. For a Q-model, the lead time is 3 days.if the mean and standard deviation of demand are 40 and 30 units respectively.what

 . M 4. For a Q-model, the lead time is 3

. M 4. For a Q-model, the lead time is 3 days.if the mean and standard deviation of demand are 40 and 30 units respectively.what would be the standard deviation of demand during lead time. 32 units QL 52 units 72 units 92 units