Question: MAJOR SUBPROJECTS / ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION ( WEEKS ) Product Specifications ( P ) Market research P 1 6 Overall product specifications P

MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS)
Product Specifications (P)
Market research P16
Overall product specifications P2 P16
Hardware P3 P25
Software P4 P36
Supplier specifications (S)
Hardware S1 P45
Software S2 P46
Product design (D)
Battery D1 S11
Display D2 S14
Camera D3 S11
Outer cover D4 D1, D2, D34
Product integration (I)
Hardware I1 D43
User interface I2 D26
Software coding I3 I26
Prototype testing I4 I1, I34
Subcontracting (V)
Suppliers selection V1 S1,S210
Contract negotiation V2 I4, V16

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!