Question: Make a grant chart and a networking (CPM/PERT) with these information: A project that evaluate the competitiveness amongst local area ( no products, specifically in

Make a grant chart and a networking (CPM/PERT) with these information:
A project that evaluate the competitiveness amongst local area ( no products, specifically in Ho Chi Minh, Viet Nam):
Make a grant chart and a networking (CPM/PERT)
Gant Chart not Grant Chart*
Durations 58 Number Activity 1 Survey 2 Specification 3 Planning 4 Detail Start Date End Date 25th December, 2020 20th February, 2021 21th February, 2021 6th March, 2021 7th March, 2021 27th March, 2021 28th March, 2021 10th April, 2021 14 21 14 5 Development/ Competitiveness 11th April, 2021 8th May, 2021 49 28 6 7 Testing Documentation 9th May, 2021 6th June, 2021 5th June, 2021 3rd July, 2021 28

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!