Question: Make gantt chart and Critical Path Method use WSB Dictionary Identification: WP Code: 1.1 WP Name: Fees Deliverables: Fees will be collected for the registration

Make gantt chart and Critical Path Method use WSB Dictionary

Identification:
WP Code: 1.1 WP Name: Fees
Deliverables: Fees will be collected for the registration of the ceremony.
Resource Requirements:
Human Resources: Registrar Quantity: 120
Work Package Budget: $18,000
Predecessor(s): -
Schedule: (days) 2
Identification:
WP Code: 1.2 WP Name: Regalia
Deliverables: Ragalias will be arranged according to the number of students.
Resource Requirements:
Human Resources: Registrar Quantity: 150
Work Package Budget: $15,000
Predecessor(s): 1.1
Schedule: (days) 2
Identification:
WP Code: 1.3 WP Name: Student list
Deliverables: List of students will be made after collecting fees.
Resource Requirements:
Human Resources: Registrar Quantity: 2
Work Package Budget: $200
Predecessor(s): 1.1
Schedule: (days) 2
Identification:
WP Code: 1.4 WP Name: Awards
Deliverables: Number of awards will be ordered according to the number of students.
Resource Requirements:
Human Resources: Registrar Quantity: 50
Work Package Budget: $7,500
Predecessor(s): 1.3
Schedule: (days) 2
Identification:
WP Code: 1.5 WP Name: Caps
Deliverables: Caps will be arranged according to the number of students.
Resource Requirements:
Human Resources: Registrar Quantity: 150
Work Package Budget: $6,000
Predecessor(s): 1.1
Schedule: (days) 2
Identification:
WP Code: 2.1 WP Name: Professors
Deliverables: Professors will be invited to give degrees to the students
Resource Requirements:
Human Resources: Organisor Quantity: 20
Work Package Budget: $4,000
Predecessor(s): 1.3
Schedule: (days) 2 hours
Identification:
WP Code: 2.2 WP Name: Students
Deliverables: Students will be invited to get their degrees.
Resource Requirements:
Human Resources: Organisors Quantity: 120
Work Package Budget: -
Predecessor(s): 1.3
Schedule: (days) 2hours
Identification:
WP Code: 2.3 WP Name: Speakers
Deliverables: Speakers will be invited to motivate students.
Resource Requirements:
Human Resources: Organisor Quantity: 8
Work Package Budget: $2,400
Predecessor(s): 1.3
Schedule: (days) 2 hours
Identification:
WP Code: 2.4 WP Name: Guests
Deliverables: Parents and other guests will be invited to motivate students.
Resource Requirements:
Human Resources: Organisor Quantity: 50
Work Package Budget: -
Predecessor(s): 1.3
Schedule: (days) 3hours
Identification:
WP Code: 3.1 WP Name: Decoration
Deliverables: Decoration according to the theme of the graduation.
Resource Requirements:
Human Resources: Decorator Quantity: 2
Work Package Budget: $50,000
Predecessor(s): 1.1,2.1
Schedule: (days) 1
Identification:
WP Code: 3.2 WP Name: Stage
Deliverables: Stage needs to be prepared for guests to speak and for students to get their degrees.
Resource Requirements:
Human Resources: Decorator Quantity: 1
Work Package Budget: $30,000
Predecessor(s): 1.3.1.1
Schedule: (days) 6hours
Identification:
WP Code: 3.3 WP Name: Chairs
Deliverables: Chairs for guests and students to sit.
Resource Requirements:
Human Resources: Decorator Quantity: 200
Work Package Budget: $7,500
Predecessor(s): 3.2
Schedule: (days) 8hours
Identification:
WP Code: 3.4 WP Name: Tables
Deliverables: Tables are required to keep the awards and degrees of the students.
Resource Requirements:
Human Resources: Decorator Quantity: 7
Work Package Budget: $6,400
Predecessor(s): 3.3
Schedule: (days) 2hours
Identification:
WP Code: 3.5 WP Name: Projector
Deliverables: Projector to show student's achievements.
Resource Requirements:
Human Resources: Organisor Quantity: 1
Work Package Budget: $10,000
Predecessor(s): 3.2
Schedule: (days) 3hours
Identification:
WP Code: 4.1 WP Name: Caterers
Deliverables: Caterers are required to decide lunch for all the students and guests.
Resource Requirements:
Human Resources: Caterers Quantity: 1
Work Package Budget: $80,000
Predecessor(s): 1.5
Schedule: (days) 2
Identification:
WP Code: 4.2 WP Name: Menu
Deliverables: Menu will be decided according to the requirement of the guests and students.
Resource Requirements:
Human Resources: Caterer Quantity: 1
Work Package Budget: $50,000
Predecessor(s): 4.1
Schedule: (days) 3hours
Identification:
WP Code: 4.3 WP Name: Raw Material
Deliverables: Raw material is required to prepare lunch.
Resource Requirements:
Human Resources: Caterer Quantity: 1
Work Package Budget: $75,000
Predecessor(s): 4.2
Schedule: (days) 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!