Question: MAKE SURE ITS ACTIVITY ON ARROW DIAGRAM (not the ones that have been posted... i will downvote) 3. Construct an Activity-on-Arrow (AOA) network and an

MAKE SURE ITS ACTIVITY ON ARROW DIAGRAM (not the ones that have been posted... i will downvote)
3. Construct an Activity-on-Arrow (AOA) network and an Activity-on-Node (AON) network for a project comprised of activities A to P that satisfies the following precedence relationships. - A,B, and C, the first activities of the project, can be executed concurrently. - D,E, and F follow A. - I and G follow both B and D. - H follows both C and G. - K and L follow I. - J succeeds both E and H. - O succeeds M and I. - P succeeds J,L, and O. - K,N, and P are the terminal activities of the project