Question: Make the Network diagram for one of the examples. Make Critical Path for the same Slack for the Task G And J Task Name Duration
- Make the Network diagram for one of the examples.
- Make Critical Path for the same
- Slack for the Task G And J
| Task Name | Duration (Days) | Predecessor |
| A | 5 | - |
| B | 4 | A |
| C | 3 | B |
| D | 2 | A, C |
| E | 1 | D, B |
| F | 1 | D |
| G | 7 | E |
| H | 8 | G |
| I | 5 | G, F |
| J | 4 | I |
| K | 3 | H, J |
| L | 3 | K |