Question: Make the Network diagram for one of the examples. Make Critical Path for the same Slack for the Task G And J Task Name Duration

  1. Make the Network diagram for one of the examples.
  2. Make Critical Path for the same
  3. Slack for the Task G And J
Task Name Duration (Days) Predecessor
A 5 -
B 4 A
C 3 B
D 2 A, C
E 1 D, B
F 1 D
G 7 E
H 8 G
I 5 G, F
J 4 I
K 3 H, J
L 3 K