Question: show work please Managers are using PERT to manage their project The project has the following Activities, Activity times, and predecessors. Activity MIN, MOST LIKELY,

show work please Managers are using PERT to show work please
Managers are using PERT to manage their project The project has the following Activities, Activity times, and predecessors. Activity MIN, MOST LIKELY, MAX Predecessor A 3, 6, 12 B 12.4, 6 A 4. 5.9 A D 1.4.4 B E 3.3.3 CD The VARIANCE of the expected project completion time is: a A 1.71 B. 2.94 C. 3.866 D. 1.97 5.33