Question: Margin Below is a crew make up with rates. Assuming this crew can excavate 5 7 5 CY / HR , determine the total cost

Margin Below is a crew make up with rates. Assuming this crew can excavate 575 CY/ HR, determine
the total cost of the operation if your QTO says you need to move 72,000 CY. Assume an 8 hour day.
Equipment Qty Hourly Rate Category Cost
PU Truck 2 $10 Equipment
Scrapers 6 $120 Equipment
Push Cat (Dozer)1 $100 Equipment
14 G Motor Grader 1 $110 Equipment
Sub Total Equipment
Labor
Oper Foreman 1 $90 Labor
Scraper Oper 6 $85 Labor
Grade Checker 1 $80 Labor
Push Cat Oper 1 $83 Labor
Blade Oper 1 $88 Labor
General Laborer 2 $68 Labor
Sub Total Labor
Subs
Water Truck 1130 Subcontractors
Total
1. Determine the total direct cost of this operation
Total CY to Move 72,000
Total Crew Hours at 575 CY/ Crew Hour =______________Crew Hours
Total Crew Cost per Hour $____________________
Total Operation Direct Cost $_____________________

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Civil Engineering Questions!