Question: Mario is a construction manager working for a general contractor, he wants to demonstrate to the owner the need for time extension of the project.

Mario is a construction manager working for a general contractor, he wants to demonstrate to the owner the need for time extension of the project. He can do that by providing a detailed: A-Contingency analysis B-Scope creep analysis C- Project Plan D- Schedule analysis