Question: Mario is a construction manager working for a general contractor, he wants to demonstrate to the owner the need extension of the project. He can
Mario is a construction manager working for a general contractor, he wants to demonstrate to the owner the need extension of the project. He can do that by providing a detailed: A-Contingency analysis B- Schedule analysis C-Project Plan D- Scope creep analysis
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
