Question: Mario is a construction manager working for a general contractor, he wants to demonstrate to the owner the need for time extension of the project.
Mario is a construction manager working for a general contractor, he wants to demonstrate to the owner the need for time extension of the project. He can do that by providing a detailed: A Project Plan B Schedule analysis C Scope creep analysis D) Contingency analysis