Question: Master Production Schedule: -Weeks- Part 1 2 3 4 5 6 7 8 9 A 0 50 100 100 250 0 200 0 50 Please
Master Production Schedule:
-Weeks-
Part 1 2 3 4 5 6 7 8 9
A 0 50 100 100 250 0 200 0 50
Please use MRP methodology to develop a materials requirement plan for Williston Technologies. Please show the four MRP record rows for items A through D.
Williston Technologies wishes to use MRP methodology to developing a material requirements plan for the next nine weeks. Williston Technologies has gathered the following information to work with: Bill of Materials: A D B C Current Inventory Records: Inventory Leadtime Currently Part (in weeks) Lotsize On-hand A 1 Lot-for-Lot 50 B 2 100 100 C 2 25 100 D 1 50 400