Question: Material requirements planning (MRP) schedules a planned order receipt when Group of answer choices a. The estimate of the amount of inventory available at the

Material requirements planning (MRP) schedules a planned order receipt when
Group of answer choices
a. The estimate of the amount of inventory available at the beginning of a period cannot satisfy the gross requirements for that period.
b. A scheduled receipt exists
c. A gross requirement exists
d. The estimate of the amount of inventory available at the end of a period is zero
Question 5
Which of the following is not a measure of capacity?
Group of answer choices
a. number of machine hours for a job shop
b. available seat-miles for airlines
c. annual sales dollars generated per square foot for retailers
d. Miles per hour for a car
e. number of seats for a theater
Question 6
Which of the following is not a principle of total quality management?
Group of answer choices
a. Continuous improvement
b. Employee involvement
c. Customer satisfaction
d. Competitive supplier bidding
Question 7
A major input to an MRP system is:
Group of answer choices
a. The production plan
b. The capacity plan
c. MPS start
d. MPS quantity
Question 8
Which of the following is the most likely impact of reducing the ordering cost per order for an item?
Group of answer choices
a. The order quantity will increase
b. The order point will decrease
c. The order point will increase
d. The order quantity will decrease
Material requirements planning (MRP) schedules a planned order receipt when The estimate of the amount of inventory available at the beginning of a period cannot satisfy the gross requirements for that period. A scheduled receipt exists A gross requirement exists The estimate of the amount of inventory available at the end of a period is zero Question 5 Which of the following is not a measure of capacity? number of machine hours for a job shop available seat-miles for airlines annual sales dollars generated per square foot for retailers Miles per hour for a car number of seats for a theater Question 6 Which of the following is not a principle of total quality management? Continuous improvement Employee involvement Customer satisfaction Competitive supplier bidding Question 7 A major input to an MRP system is: The production plan The capacity plan MPS start MPS quantity Question 8 Which of the following is the most likely impact of reducing the ordering cost per order for an item? The order quantity will increase The order point will decrease The order point will increase The order quantity will decrease
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts