Question: Math Problem 2-Critical Path Method Use the following network diagram and data table to complete a forward and backward pass, and answer the following

Math Problem 2-Critical Path Method Use the following network diagram and data table to complete a forward and backward pass, and answer the following questions: You can upload a photo of your network diagram to Turn-It-In 2a. What is the minimum completion time of the project in days? 2b. What is the latest time the project manager should finish Activity C without delaying the project completion time? 2c. What is the earliest time the project manager can finish Activity E. 2d What is the slack for Activity D? B E G Activity Time (days) 6 4 IT ABCDEFGH 1000005233 H
Step by Step Solution
There are 3 Steps involved in it
Certainly lets analyze the network diagram and data table to answer your questions about the project 2a What is the minimum completion time of the project in days To determine the minimum completion t... View full answer