Question: Maximum Available Crews: 13 Problem 2 Estimate the total cost to complete piping construction activities on a project. The piping construction involves 1,000 linear feet
Maximum Available Crews: 13
Problem 2
Estimate the total cost to complete piping construction activities on a project.
The piping construction involves 1,000 linear feet of piping which has been divided into 50 sections
for management convenience. At this time, 400 linear feet of piping has been installed at a cost of
$40,000 and 500 man-hours of labor. The original budget estimate was $90,000 with a productivity of
one foot per man-hour, a unit cost of $60 per man hour and a total material cost of $ 30,000. Firm
commitments of material delivery for the $30,000 estimated cost have been received.