Question: Maximum Available Crews: 13 Problem 2 Estimate the total cost to complete piping construction activities on a project. The piping construction involves 1,000 linear feet

Maximum Available Crews: 13 Problem 2 EstimateMaximum Available Crews: 13

Problem 2

Estimate the total cost to complete piping construction activities on a project.

The piping construction involves 1,000 linear feet of piping which has been divided into 50 sections

for management convenience. At this time, 400 linear feet of piping has been installed at a cost of

$40,000 and 500 man-hours of labor. The original budget estimate was $90,000 with a productivity of

one foot per man-hour, a unit cost of $60 per man hour and a total material cost of $ 30,000. Firm

commitments of material delivery for the $30,000 estimated cost have been received.

Act. | ES LS Daily Req. | a lo | |6|s| | || start 000 116 1160 finish 16011 | |0|0|0 |8 | | a ls | 11 |6 |6 |

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!