Question: MC Qu . 1 9 ( Static ) When reducing project duration, the crash...When reducing project duration, the crash cost per unit has to be

MC Qu.19(Static) When reducing project duration, the crash...When reducing project duration, the crash cost per unit has to be calculated and the maximum units each activity can be reduced must be known. After this, the critical path must be identified. What is the next step?Multiple ChoiceCalculate the optimum cost-time pointFind the activity with the lowest crash costCalculate indirect cost per time unitFind the activity with the steepest cost slopeCalculate the crash point