If for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?
Multiple Choice
Check to see which activities cost the least.
Check to see which activities have the longest duration.
Check to see which activities are on the critical path.
Check to see which activities have the most slack.
Check to see which activities have the highest risk.