Question: MC Qu . 4 3 A shift in critical path can... A shift in critical path can occur when: Multiple Choice a non - critical

MC Qu.43 A shift in critical path can...
A shift in critical path can occur when:
Multiple Choice
a non-critical path activity is running unexpectedly longer.
a critical path activity is running unexpectedly longer.
a non-critical path activity is running unexpectedly faster.
a critical path activity is delayed in starting.