Question: A shift in critical path can occur when _ _ _ _ _ _ _ _ _ blank. Multiple Choice a critical path activity is
A shift in critical path can occur when blank.
Multiple Choice
a critical path activity is running unexpectedly longer
a critical path activity is delayed in starting
a noncritical path activity is running unexpectedly faster
a noncritical path activity is running unexpectedly longer