Question: A shift in critical path can most likely occur when: a critical path activity is delayed in starting. a non-critical path activity runs unexpectedly longer
A shift in critical path can most likely occur when: a critical path activity is delayed in starting. a non-critical path activity runs unexpectedly longer than its available buffer time a non-critical path activity is running unexpectedly faster. a critical path activity is running unexpectedly longer