Question
Mega Manufacturer, Inc. ( MMI ) sought to build a new factory. MMI retained Awesome Architects, Inc. ( AAI ) , an architectural firm, to
Mega Manufacturer, Inc. MMI sought to build a new factory. MMI retained Awesome Architects, Inc. AAI an architectural firm, to create the plans and specifications and administer the project. Based upon this design, the owner entered into a $ million fixedprice contract with Prime Builder, Inc. Under the prime contract, Prime Builder was required to obtain payment and performance bonds, which it acquired from Surety, Inc. To
obtain the bonds, Prime Builder and its individual owners entered into an indemnity agreement broadly promising to reimburse Surety for its expenses incurred by or under the bond. Prime Builder hired several subcontractors, including a framing subcontractorFramer and a roofing subcontractor Roofer Framer built the building's framework with lumber purchased from a supplier. Roofer assembled materials on the site in preparation for building the roof. AAl was unhappy with the quality of the work and consistently approved only partial payments for Prime Builder. The prime contractor began cutting back on payments to subcontractors and suppliers. When these parties complained to Surety, Surety investigated and discovered that Prime Builder's finances were in disarray. On February Surety informed MMI to forward all future progress payments to it Instead, MMI sent a $ progress payment on March to its contractor. On March MMI declared Prime Builder in default and terminated the prime contract. MMI notified Surety of its actions.
On March a fire destroyed Roofers materials which were still in storage on the ground before they could be removed. On March Prime Builder wrote a long letter to Surety, explaining that its cash flow problems were caused by AAIs failure to certify payments and as a result that its termination by MMI was wrongful. The prime asked Surety not to assume its bond obligations. Instead, Surety hired Prime Builder to complete the project. MMI objected, stating that it would not allow Prime Builder back unto the site.
Question:
Using all the content you have learned in the course this semester, please evaluate this scenario from a legal perspective. I will be looking for legal terms and jargon, case law justification and citation of source of your response. You need to include at minimum a detailed discussion on bonds; surety; obligation; performance; liabilities; payments; claims; reimbursements; regulations; bankruptcy and contracts outside the USA. A plagiarism check will be run on your Exam. Limit your response to no more than pages, single spaced, size font. No more than graphs or tables if applicable.
Questions: Use legal terminology and a case law citations. Please provide an example of a connection to the textbook case with a citation
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Conversation with Gemini expandmoreedit Mega Manufacturer IncMMIsought to build a new factory MMI retained Awesome Architects IncAAIan architectural firm to create the plans and specifications and adm...Get Instant Access with AI-Powered Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started