Question: MGMT 6 4 0 . Week 4 Network Practice Exercise Including Online Forum Participation Shoreline Baseball Stadium Project. ID Activity Duration Predecessor ( s )
MGMT Week Network Practice Exercise Including Online Forum Participation
Shoreline Baseball Stadium Project.
ID Activity Duration Predecessors
Clear stadium site days
Demolish existing building days
Set up construction site days
Drive support piling days
Pour lower concrete bowl days
Pour main concourse days
Install playing field days
Construct upper steel bowl days
Install seats days
Build luxury boxes days
Install jumbotron days
Stadium infrastructure days
Construct steel canopy days
Light installation days
Build roof supports days
Construct roof days
Install roof tracks days
Install roof days
Inspection days
Cleanup days
Exercise:
Develop the network diagram for the Shoreline Baseball Stadium Project using the details
provided in the table above. marks
Carry out the Forward and backward Passes. Ensure t
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
