Question: MGMT 6 4 0 . Week 4 Network Practice Exercise Including Online Forum Participation Shoreline Baseball Stadium Project. ID Activity Duration Predecessor ( s )

MGMT 640. Week 4 Network Practice Exercise Including Online Forum Participation
Shoreline Baseball Stadium Project.
ID Activity Duration Predecessor(s)
1 Clear stadium site 70 days -
2 Demolish existing building 30 days 1
3 Set up construction site 70 days 2
4 Drive support piling 120 days 1
5 Pour lower concrete bowl 120 days 4
6 Pour main concourse 120 days 3,5
7 Install playing field 90 days 3,5
8 Construct upper steel bowl 120 days 3,5
9 Install seats 140 days 6,8
10 Build luxury boxes 90 days 6,8
11 Install jumbotron 30 days 6,8
12 Stadium infrastructure 120 days 6,8
13 Construct steel canopy 75 days 9
14 Light installation 30 days 13
15 Build roof supports 90 days 5
16 Construct roof 180 days 15
17 Install roof tracks 90 days 15
18 Install roof 90 days 16,17
19 Inspection 20 days 7,10,11,12,14,18
20 Cleanup 21 days 19
Exercise:
Develop the network diagram for the Shoreline Baseball Stadium Project using the details
provided in the table above. 20 marks

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!