Question: MGMT 6 4 0 . Week 4 Network Practice Exercise Including Online Forum Participation Shoreline Baseball Stadium Project. ID Activity Duration Predecessor ( s )

MGMT 640. Week 4 Network Practice Exercise Including Online Forum Participation
Shoreline Baseball Stadium Project.
ID Activity Duration Predecessor(s)
1 Clear stadium site 70 days -
2 Demolish existing building 30 days 1
3 Set up construction site 70 days 2
4 Drive support piling 120 days 1
5 Pour lower concrete bowl 120 days 4
6 Pour main concourse 120 days 3,5
7 Install playing field 90 days 3,5
8 Construct upper steel bowl 120 days 3,5
9 Install seats 140 days 6,8
10 Build luxury boxes 90 days 6,8
11 Install jumbotron 30 days 6,8
12 Stadium infrastructure 120 days 6,8
13 Construct steel canopy 75 days 9
14 Light installation 30 days 13
15 Build roof supports 90 days 5
16 Construct roof 180 days 15
17 Install roof tracks 90 days 15
18 Install roof 90 days 16,17
19 Inspection 20 days 7,10,11,12,14,18
20 Cleanup 21 days 19

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!