Question: MGT - 6 4 0 Project Risk Assessment Problems Template ID Task Optimistic Duration ( days ) Most Likely Duration ( days ) Pessimistic Duration

MGT-640 Project Risk Assessment Problems Template
ID Task Optimistic Duration (days) Most Likely Duration (days) Pessimistic Duration (days) PERT Expected Duration (days) Critical Path Variance
1 TECHNOLOGY REFRESH (VERSION B) PROJECT
2 Initiating
3 Meet with key stakeholders 23124
4 Finalize statement of work 2101510
5 Secure project team leads 2242
6 Finalize stakeholder register 210139
7 Develop project charter 25177
8 Finalize project charter 2484
9 Planning
10 Scope Planning
11 Requirements
12 Develop/finalize functional requirements 10182818
13 Develop/finalize hardware requirements 12161816
14 Develop/finalize software requirements 10163017
15 Develop/finalize requirements traceability matrix 11142816
16 Finalize project deliverables 2232
17 Develop scope statement 49108
18 Finalize/Update WBS 2353
19 Schedule (Time) and Cost Planning
20 Finalize hardware/software costs 2454
21 Update activities and duration estimates 6121411
22 Human Resource Planning
23 Finalize resource requirements 6101410
24 Finalize project costs 4111911
25 Identify training requirements 2454
26 Complete training activities 6121411
27 Quality Planning
28 Determine impacted quality processes 2343
29 Finalize quality management plan 2101810
30 Risk Planning
31 Update project risks 36127
32 Draft risk register 2384
33 Finalize risk management plan 2474
34 Finalize Project Plan
35 Finalize communications management plan 2343
36 Finalize procurement management plan 26147
37 Finalize stakeholder management plan 2253
38 Finalize project schedule/cost baseline 2131912
39 Finalize project plan 25166
40 Obtain approval for project plan 2474
41 Executing
42 Hardware
43 Procure hardware from suppliers 10243223
44 Software
45 Obtain software OS licenses 6112012
46 Obtain software application licenses 68179
47 Pilot Testing
48 Setup test area 1222
49 Load software onto pilot machines 4686
50 Validate functionality 3686
51 Deployment
52 Configure production hardware 10253324
53 Deploy production hardware 11192318
54 Load software to deployed hardware 12171917
55 Testing
56 Validate startup on deployed hardware 491810
57 Perform OS testing 48179
58 Perform application testing 4192818
59 Obtain formal sign-off from users 6172416
60 Monitoring and Controlling
61 Formal Customer Review 1
62 Hold formal customer review after project plan approval 1343
63 Update project plan 4102011
64 Formal Customer Review 2
65 Obtain updates regarding key deliverables from project team 5182217
66 Hold formal customer review after pilot testing 57117
67 Update project plan 48159
68 Closing
69 External
70 Finalize procurement with suppliers 5182417
71 Customer Approval
72 Hold final customer review 1222
73 Prepare/submit final customer report 36106
74 Audit against contractual deliverables 3585
75 Obtain final customer approval 2343
76 Internal
77 Hold lessons learned meeting 1111
78 Update final internal report 46127
79 Hold project team celebration event 1121
Expected Project Finish Time: Total Critical Path Variance: days
days
Total Critical Path Standard Deviation: days
Probability of finishing the project in 287 days is
or
%
Probability of finishing the project in 273 days is
or
%

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!