Question: minutes An assembly process is depicted below: 09 B Sub-process A takes 6 minutes, sub-process B takes 9 minutes, and the sub-process C, which assembles

minutes An assembly process is depicted below: 09minutes

An assembly process is depicted below: 09 B Sub-process A takes 6 minutes, sub-process B takes 9 minutes, and the sub-process C, which assembles the inputs from A and B, takes 3 minutes. What is the possible daily output of this assembly process, assuming an eight hour work day? (Provide one decimal place)