Question: Module 4 Case Study Transcript Ava Richardson, VP of Operations, emails Charlie and asks him how long the project will take. Charlie knows the answer

Module 4 Case Study Transcript
Ava Richardson, VP of Operations, emails Charlie and asks him how long the project will take. Charlie knows
the answer to that question; he must begin building out the schedule and identify the Critical Path.
Step 1:
Using the data set, draw a network diagram (Fig 6.4) and complete a forward and backward pass (Fig 6.6
and 6.7).
What activities are on the critical path (Fig 6.8)?
What is the project duration?
Step 2:
Build the Gantt Chart (6.11).
Activity
(Bolded is the deliverable)
Most Likely
Duration
(unit = days)
Immediate
Predecessor
1 AT Data Center Project
21.1 Team Meeting 1
31.2 Hire Contractors 72
41.3 Network Design 142
51.4 Ventilation System
61.4.1 Order Ventilation System 212
71.4.2 Install Ventilation System 76
81.5 New Racks
91.5.1 Order Racks 142
101.5.2 Install Racks 219,15
111.6 Power Supplies and Cables
121.6.1 Order Power Supplies and
Cables
72
131.6.2 Install Power Supplies 512,15
141.6.3 Install Cables 812,15
151.7 Renovation of Data Center 203,4
161.8 City Inspection 27,10,13,14
171.9 Switchover Ops Checks 716
181.10 Validation Tests with Clients 1417
191.11 Project Closure Meeting 218

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!