Question: Monitoring both before and after production involves acceptance sampling procedure rather than process control. 2 . Variables must be counted rather than measured. 3 .

Monitoring both before and after production involves acceptance sampling procedure rather than process control.
2. Variables must be counted rather than measured.
3. The LTPD (lot tolerance percent defective) is associated with a producer's risk rather than a consumer's risk..
4. The primary tool used in acceptance sampling is the control chart rather than operating characteristic(OC) curve.
5. A consumer's risk is the probability of a consumer's rejecting goods which are lower in quality than requested.
6. The process control procedure in a quality control involves:
a. monitoring outputs that are part of an on-going process.
b. determining of acceptance or rejection of a lot of material.
c. monitoring both before and after production. d. both b and c are correct.
7. The two types of measurements undertaken in quality control are:
a. assignable factors and random factors. b. accuracy and precision.
c. variables and attributes. d. design and operations.
8. B(beta) risk is equal to :
a. percentage of consumer's risk. b. percentage of producer's risk.
c. overall fraction defective. d. none of the above.
9. Which of the following are important in customers' perception of quality?
I. Appearance II. Operation III. Liability
a. I only b. II only c. I and II only d. I, II, and III
10. An X-bar (or Mean) chart controls the:
a. mean of the process. b. variance of the process.
c. range of the process. d. only a and b.
11. A type I error (same as producers risk) occurs in the quality control when:
a. a bad lot is accepted. b. a good lot is accepted.
c. a good lot is rejected. d. a bad lot is rejected.
12. A C-chart is used for:
a. means. b. percent defective.
c. ranges. d. number of defects.
13.The United States Quality Award is named after:
a. Taguchi. b. Demming c. Crosby d. Baldrige.
14. A P-chart is used for:
a. acceptance sampling by attribute(s). b. acceptance sampling by variable(s).
c. process control by variable(s). d. process control by attribute(s).
15. The type of inspection that classifies items as being either good (non-defective) or bad (defective) is
a. variable inspection b. fixed inspection c. attribute inspection d. a and c are correct.
16. The Quality emphasis that encompasses the entire organization, from supplier to customer is:
a. JIT techniques. b. TQM c. Benchmarking. d. ISO 9000
SAMPLE TEST FOR PROJECT MANAGEMENT & ASSIGNMENT METHOD..
1. The forward pass involves the calculation of LS time and LF time.
___2. In the assignment method, it is possible to assign one job to more than one work station if necessary.
3. PERT and CPM are different in the fact PERT is probabilistic; while CPM is deterministic.
4. PERT stands for Project Evaluation and Review Technique while CPM stands for Critical Path Method.
5. A delay in an activity on the critical path does not necessarily mean a delay in the overall project.
____6. In PERT/CPM, the critical path of a network is the longest time path through the network..
___7. A dummy activity may be used in PERT and CPM to describe a resources restriction in the project .
8. If an activity has a zero slack in PERT/CPM, it means the project will be affected by its activity on that network path.
9. A delay in an activity on the critical path method (CPM) does not necessarily mean a delay in the overall project.
10. Which of the following is not true of the critical path?
a. critical path can not be changed during the life of project.
b. critical path is always longest in a network.
c. critical path demands careful monitoring and controlling.
d. all of the answers are correct.
____11. Which two terms reflect the scheduling in the job shops?
a. Line balancing and flow control. b. Assignment Method and Appointment.
c. Gantt chart and run-out time. d. Loading and Sequencing.
____12. If an activity has a zero slack time, it:
a. means the project is expected to delayed. b. must be a dummy activity.
c. is on the critical path. d. all are correct.
SAMPLE TEST-SUPPLY CHAIN MANAGEMENT
__1. Because service firms do not acquire goods and services externally, their supply chain management
issues are insignificant.
__2. Which of the following strategy terms describes the coordination of all supply chain activities, starting with
raw materials and ending with a satisfied customer.
a. Supply chain management. b. Logistic algorithm c. Make-or-Buy decision. d. Keiretsu
__3. Inventory turnover can be measured by:
a. Costo goods sold -: Weeks of supply b. Weeks of supply -: Annual cost of goods sold
c. Cost of goods sold -: Average inventory investment. d. Average inventory investment -: Cost of goods sold.
__4. A major issue in Logistics is:
a. Cost of purchase. b. supplier evaluation c. product customization d. cost of shipping alternatives.
__5. Supplier selction requires:
a. Supplier evaluation and effective third-party logistics. b. supplier development and logistics.
c.. Negotiations, supplier evaluation, sup

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!