Question: More Info begin{tabular}{ccccc} hline & multicolumn{5}{c}{TimeEstimates(days)MostActivity} & Optimistic & Likely & Pessimistic & ImmediatePredecessor(s) hline A & 4 & 7 & 8 & -

 More Info \begin{tabular}{ccccc} \hline & \multicolumn{5}{c}{TimeEstimates(days)MostActivity} & Optimistic & Likely &
Pessimistic & ImmediatePredecessor(s) \\ \hline A & 4 & 7 & 8
& - \\ B & 7 & 8 & 11 & -

More Info \begin{tabular}{ccccc} \hline & \multicolumn{5}{c}{TimeEstimates(days)MostActivity} & Optimistic & Likely & Pessimistic & ImmediatePredecessor(s) \\ \hline A & 4 & 7 & 8 & - \\ B & 7 & 8 & 11 & - \\ C & 2 & 4 & 5 & - \\ D & 11 & 18 & 26 & A \\ E & 7 & 10 & 13 & B \\ F & 3 & 4 & 5 & C,E \\ G & 3 & 8 & 9 & D \\ H & 5 & 7 & 8 & F \\ I & 7 & 11 & 16 & G, H \\ J & 4 & 4 & 4 & G \\ \hline \end{tabular} must be done and thelr relationshipe to each oluebiversity just approved the planning for a sales training seminar Heir adminktrativer atsiestant identfind the vacious ackivifes that Click the icon to view the acthitins Because of the uncertainty in planning the naw course, the assistant alse has supplied the folowing flme estimatis for each activily Click the icon to view the time estimates The director wants to conduct the seminar 46 working days from now. What is the probabiaty that everything wil be ready in time? Refer to the round all intermediate calculations for te and vanance to two decimal placos) The probability that the seminar will be ready in time is (Enter your response rounded fo four decimal placos)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!