Question: MPS Record Lot Size: L4L Lead Time: 1 weeks Quantity on Hand (Period 0): 50 Week 1 2 3 4 5 6 7 8 Gross

MPS Record

  • Lot Size: L4L
  • Lead Time: 1 weeks
  • Quantity on Hand (Period 0): 50
Week 1 2 3 4 5 6 7 8
Gross Requirements 50 20 30 40 20
Scheduled Receipts
Projected on-hand inventory
Planned Receipts
Planned Order Releases

Using the data seen above?

What are the quantities of planned order releases for this item for the first six weeks (weeks 1, 2, 3, 4, 5, and 6)?

Group of answer choices

A. 5, 30, 0, 40, 20, 0

B. 20, 30, 0, 40, 20, 0

C. 35, 0, 0, 40, 20, 0

D. 35, 0, 60, 0, 0, 0