Question: MPS Record Lot Size: P=2 Lead Time: 2 weeks Quantity on Hand (Period 0): 0 Week 1 2 3 4 5 6 7 8 Gross
MPS Record
Lot Size: P=2
Lead Time: 2 weeks
Quantity on Hand (Period 0): 0
Week 1 2 3 4 5 6 7 8
Gross Requirements 30 30 60 75 70
Scheduled Receipts 60
Projected on-hand inventory
Planned Receipts
Planned Order Releases
Using the data seen above.
What are the quantities of planned order releases for this item for the first five weeks (weeks 1, 2, 3, 4, and 5)?