Question: MRP: Consider the MPS, BOM, and inventory data shown. Master Production Schedule: Table below shows the MPS start quantities (planned order releases). Time Period 1

MRP: Consider the MPS, BOM, and inventory data shown.

Master Production Schedule: Table below shows the MPS start quantities (planned order releases).

Time Period

1

2

3

4

5

6

7

8

End-Item P1 MPS Start Quantities

20

40

30

End-Item P2 MPS Start Quantities

25

15

20

Bill of Material: - Item P1 uses 1 each of subassembly A and 2 each of component B.

- Item P2 uses 1 each of subassembly A and 3 each of component C. - Subassembly A is made from 3 each of component D.

Selected Inventory Data:

Item

Lot Size Technique

Lead Time

Scheduled Receipts

On-Hand

Safety Stock

A

L4L

1

30

5

B

FOP, P=3

2

20 in period 2

20

C

FOQ=75

1

75 in period 1

10

D

L4L

2

40

1, Construct the MRP tables for items A, B, C, and D using the preceding information. The key row of interest is the Planned Order Releases; you may choose not to complete the Net Requirements Row. Specify all Action Notices corresponding to actions that must be implemented in Week 1 or earlier. If appropriate, use the MRP tables provided at the end of this assignment. Acronym Key: GR = Gross Requirements; SR = Scheduled Receipts, POHEI = Projected On Hand End-of-period Inventory, NR = Net Requirements, PR = Planned Receipts, POR = Planned Order Releases

2. What is MRP-II and why was it created? What does ERP add to MRP-II?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!