Question: MRP X Use the information below to work the problems in this section and the next three sections. Read the instructions in each section that
MRP X
Use the information below to work the problems in this section and the next three sections. Read the instructions in each section that follows fully and carefully.
Each X is made of 2Y and 1Z
Each Y is made of 3A and B
Each Z is made of 5A and C
We will ignore scheduling B and C
Inventory information is as follows:
X
Lot size 1,200
On hand 1,100
Safety stock 300
Allocated 0
Lead time 1
Gross requirements for periods 1-8 are: 600, 700, 600, 700, 600, 700, 600, and 700.
What is the projected on hand at the end of period 1-8? What are the net requirements in period 1-8? What are the planned order releases in period 1-8?
Please explain your answers.
This is the feedback from my professor but I am still confused how to end up with the table.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock