Question: Use the information below to work the problems in this section and the next three sections. Read the instructions in each section that follows fully

Use the information below to work the problems in this section and the next three sections. Read the instructions in each section that follows fully and carefully.

  • Each X is made of 2Y and 1Z
  • Each Y is made of 3A and B
  • Each Z is made of 5A and C
  • We will ignore scheduling B and C

Inventory information is as follows:

X
Lot size 1,200
On hand 1,100
Safety stock 300
Allocated 0
Lead time 1

Gross requirements for periods 1-8 are: 600, 700, 600, 700, 600, 700, 600, and 700.

There is a separate section for X, Y, Z, and A. Some information changes between sections.

Please explain your answer.

This is the feedback from the professor but I am confused how do we get the data on the table? Use the information below to work the problems in
What is the projected on hand at the end of period 1? Answer: x (200) Hide Feedback 600 700 600 700 600 700 600 700 600 800H Gross Requirements Scheduled Receipts Projected on Hand (Begin) Projected on Hand (End) Net Requirements Planned Order Receipts Planned Order Releases 8001 200 1.100 400 200 700 500 1.2001 100 600 600 1.2001 500 700 1.200 1.200 500 1.100 100 1.200 1,200 1,200 1.200 Question 141 What is the projected on hand at the end of period 2? Answer: * (700) View Feedback

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!