Question: MS Project Lab 1 : Use ERM Project file provided. You have only 8 design engineers to finish the work. ( Resource Constraint ) .

MS Project Lab 1:
Use ERM Project file provided.
You have only 8 design engineers to finish the work. (Resource
Constraint).
Develop a Resource constraint schedule by leveling the slack. Use Leveling
tool in MS Project. This may not solve all allocation problems and you may
want to use scheduling heuristics and level outside of the slack.
Record the Early Start, late Finish, and Slack for the new schedule.
Each Engineer cost is $125 per hour. Plug in the rate and set up baseline
budget for the new schedule.
You need to submit MS Project file with updated schedule with all
allocation concerns solved and total baseline budget.
Also Provide your synopsis on how you slack changed for each activity. Has
the risk of being late is changed? How?
 MS Project Lab 1: Use ERM Project file provided. You have

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!