Question: Consider the following data for a project: Activity Time (days) Immediate Predecessor(s) A2 B4 A C5 A D2 B E1 B F 8 B,
Consider the following data for a project: Activity Time (days) Immediate Predecessor(s) A2 — B4 A C5 A D2 B E1 B F 8 B, C G 3 D, E H5 F I4 F J 7 G, H, I
a. Draw the network diagram.
b. Calculate the critical path for this project.
c. How much slack is in each of the activities G, H, and I?
Step by Step Solution
3.34 Rating (160 Votes )
There are 3 Steps involved in it
a The network diagram is given below b Critical path is ACFHJ c Activity G Latest e... View full answer