Question: Question 26 19 pts Earned Value Problem: 25 points total This problem is divided into three parts. Earned Value Problem - Part 1 Your project

 Question 26 19 pts Earned Value Problem: 25 points total This

Question 26 19 pts Earned Value Problem: 25 points total This problem is divided into three parts. Earned Value Problem - Part 1 Your project is tasked with excavation of 1,000,000 cubic feet of soil. According to the project management plan you need to excavate 60,000 cubic feet of soil per week at a cost of $5 per cubic feet. According to the first month's progress report the project's EV was 1,000,000 and the AC was 1,200,000. According to the second month's progress report the project's EV was 2,200,000 and the AC was 3,400,000. After the 3rd month (12 weeks) you have 250,000 cubic feet of soil remaining to be excavated and your total cost to date is 4,000,000. Determine the current values for the project for each of the terms below after the 3rd month: Term Value Budget at completion $ Planned Value Earned Value Actual Cost $ Cost Variance $ Schedule Variance $ Cost Performance Index Schedule Performance Index Estimate at Completion $ Estimate to Completion $ Variance at Completion $

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!