Question: Multiple choice ( no need for explanation) 1) A project must end by a pending deadline and is running late because of a lack of
Multiple choice ( no need for explanation)
1) A project must end by a pending deadline and is running late because of a lack of resources. Which of the following methods could help the project end on time?
a. Procurement
b. Change control
c. Risk assessment
2) Where is process improvement expected to be executed?
a. Monitor and Control Project Work
b. Plan Quality Management
c. Control Quality
d. Manage Quality
3) Which of the following statements is NOT true about risk identification?
a. The WBS plays an important role in identifying risks.
b. The data about risks is assessed during identifying risks to ensure it is qualified for further use.
c. The project team is involved in identifying risks.
d. The risk breakdown structure is helpful in identifying risks.
4) During the initiation processes, in addition to creating the project charter, what other activity should you complete?
a. Stakeholder engagement
b. Stakeholder identification
c. Project risk identification
d. Push communications to stakeholders
5)
Both projects and operations share all the following characteristics EXCEPT:
a. Limited by constraints
b. Performed to achieve the strategic objectives of the organization
c. Performed by individuals
d. Planned, executed, monitored, controlled, and closed in a preplanned way