Question: Multiple critical paths are anticipated in the project shown below. What is the length of the critical path(s) and how many different critical paths are
Multiple critical paths are anticipated in the project shown below. What is the length of the critical path(s) and how many different critical paths are there?
| Task | C | D | E | F | G | H | I | J | K |
| Immed Predecessor |
| C | C | C | D | E, G | H | H | F |
| Duration | 2 | 8 | 7 | 11 | 3 | 4 | 6 | 4 | 10 |