Question: n 8. Given the following network, D7 A8 G5 C3 E6 E Start End IXT F7 H3 (a) What is the critical path? (b) How


n 8. Given the following network, D7 A8 G5 C3 E6 E Start End IXT F7 H3 (a) What is the critical path? (b) How long will it take to complete this project? (c) Can activity B be delayed without delaying the completion of the project? If so, how many days