Question: n a PERT/CPM network, computing the critical path requires a. Determining the total project duration b. Assigning the earliest finish time for an activity as
n a PERT/CPM network, computing the critical path requires
a.
Determining the total project duration
b.
Assigning the earliest finish time for an activity as the earliest start time for the
next
c.
That the latest finishing time for an activity not delay the overall project beyond
initial expectation
d. A sophisticated and complex computer program
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
