In a PERT/CPM network, computing the critical pathrequires a. determining the total project duration b. assigning the
Fantastic news! We've Found the answer you've been seeking!
Question:
In a PERT/CPM network, computing the critical pathrequires
a. determining the total project duration
b. assigning the earliest finish time for an activity as theearliest start time for the next
c. that the latest finishing time for an activity not delay theoverall project beyond initial expectation
d. a sophisticated and complex computer program