Question: In a PERT/CPM network, computing the critical pathrequires a. determining the total project duration b. assigning the earliest finish time for an activity as theearliest
In a PERT/CPM network, computing the critical pathrequires
a. determining the total project duration
b. assigning the earliest finish time for an activity as theearliest start time for the next
c. that the latest finishing time for an activity not delay theoverall project beyond initial expectation
d. a sophisticated and complex computer program
Step by Step Solution
3.44 Rating (151 Votes )
There are 3 Steps involved in it
b assigning the earliest finish time for an activity as theearliest start time for the next In other ... View full answer