Question: N The table below shows the complete project plan and includes all the activities with its immediate predecessor activity and time taken by each


N The table below shows the complete project plan and includes all the activities with its immediate predecessor activity and time taken by each activity. ANSWER THE FOLLOWING QUESTION Activity Preceding Activity Time (Weeks) of A None 7 B None 8 stion C None 6 D A 6 E B 6 F B 8 G C 4 H D.E 7 F,G,H 3 What is the earliest finish (EF) of activity 1? Choose... What is the latest start (LS) of activity F? What is the slack (SL) value of activity H? What is the slack (SL) value of activity G? Wir What is the latest finish (LF) of activity G? Dws Choose.... Choose.... Choose... Choose... What is the earliest start (ES) of activity G? Choose...