Question: Name ID Multiple Activity Chart Operator Machine 2 2 machine and 1 operator Loading: 1 min Machine automated operating time: 8 min Traveling time: 2
Name
ID
Multiple Activity Chart
Operator
Machine
machine and operator
Loading: min
Machine automated operating time: min
Traveling time: min
Unloading: min
Inspecting and Packing: min
Operator Cost $ hour
Machine Cost $ hour
a Construct a multiple activity chart.
b What is the transient time?
c Determine the cycle length cycle time
d Determine machine idle time during a repeating cycle
e Determine operator idle time during a repeating cycle
f Determine ideal machine assignment
g Calculate unit production cost if you assign nearest integer number of machines that is greater than ideal
h Calculate unit production cost if you assign nearest integer number of machines that is less than ideal
i Compare costs and what would be your recommendation
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock