Question: Name ID Multiple Activity Chart Operator Machine 2 2 machine and 1 operator Loading: 1 min Machine automated operating time: 8 min Traveling time: 2

Name
ID
Multiple Activity Chart
Operator
Machine 2
2 machine and 1 operator
Loading: 1 min
Machine automated operating time: 8min
Traveling time: 2min
Unloading: 1min
Inspecting and Packing: 3min
Operator Cost $20? hour
Machine Cost $10? hour
a) Construct a multiple activity chart.
b) What is the transient time?
c) Determine the cycle length (cycle time).
d) Determine machine idle time during a repeating cycle
e) Determine operator idle time during a repeating cycle
f) Determine ideal machine assignment
g) Calculate unit production cost if you assign nearest integer number of machines that is greater than ideal
h) Calculate unit production cost if you assign nearest integer number of machines that is less than ideal
i) Compare costs and what would be your recommendation
 Name ID Multiple Activity Chart Operator Machine 2 2 machine and

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!