Question: Need entire solution with all steps Question 1 The following table gives the activities in a ship building project & other relevant information. 1. Draw
Need entire solution with all steps
Question 1 The following table gives the activities in a ship building project & other relevant information. 1. Draw a PERT diagram. Find the expected duration and variance for each activity. 2. What is the expected project length. 3. Calculate the variance & Standard Deviation of the project length. 4. What is the possibility that the project will be completed in 69.25 weeks. 5. What is the possibility that the project will be completed in 74.25 weeks. Standard Normal Table extract given below