Question: Need help for question 2 and 3! 1. The following information is given for a particular part. Using a lead time of two weeks, complete

Need help for question 2 and 3!

Need help for question 2 and 3! 1. The following

1. The following information is given for a particular part. Using a lead time of two weeks, complete the table. Use L4L with On hand = 80 and SS = 0. Week 1 2. 3. 4 5 100 400 300 50 80 Gross requirement Scheduled receipts Projected ending inventory Net requirement Planned order receipts Planned order releases 2. Using the original information in problem 1, complete the table again, but this time assuming that the supplier requires a fixed lot size of 500 units. 3. Again using the original information in problem 1 and L4L, complete the table with a requirement of safety stock of 100 units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!