Question: Problem 15-3 (LO 15-3) The following information is given... The following Information is glven for a particular part. Using a lead time of two weeks,

Problem 15-3 (LO 15-3) The following information
Problem 15-3 (LO 15-3) The following information is given... The following Information is glven for a particular part. Using a lead time of two weeks, complete the table. Use L4L with On hand - 80 and safety stock of 100 units. Answer is complete but not entirely correct. Week 1 Week 2 Week 3 100 Week 4 400 Week 5 300 50 0 0 0 30 80 Gross requirement Scheduled receipts Projected ending inventory Net requirement Planned order receipts Planned order releases 300 70 170 300 400 400 OOOO 300 0 0 > 170 400